Data Center Emergency Preparedness: What Fire, EMS and the Operator Should Settle Before Energization

By Joel Yonkman · November 18, 2026 · 5 min read

The ribbon cutting is not the deadline that matters. Energization is. Once utility power flows into the substation and the battery rooms charge, the campus holds stored energy, fuel and chemicals that the local fire department will be asked to handle on its worst night. Every question the operator and the responding agencies have not answered by then gets answered under pressure.

What a county should require at approval is a separate question. This article is narrower: the working agreements fire, EMS, emergency management and the operator should have in hand before the switch is thrown.

Why energization is the real deadline

During construction, the main risks are the ones any large job site carries: injuries, traffic and the occasional fire in a building that is not finished. Energization changes the hazard profile in a single step. The battery systems are live. Generators and fuel tanks are in service. Security systems start limiting who can get through a gate. And the staff on site shift from construction crews, who know the layout, to a much smaller operations team that may not.

That is why the pre-energization checkpoint deserves its own plan, its own walk-through and its own exercise.

What should the battery and hazmat plan cover?

Large data centers rely on battery systems for backup power, and lithium-ion batteries bring a hazard that ordinary structure fire tactics do not handle well. The national standard for these installations is NFPA 855, Standard for the Installation of Stationary Energy Storage Systems. Its 2026 edition was significantly revised and added new requirements for an emergency response plan; it also addresses explosion control, exhaust ventilation, gas detection and thermal runaway (ICC listing for NFPA 855, 2026 edition). Which edition applies depends on what the state or local jurisdiction has adopted, so confirm that first.

The risk is documented. On April 19, 2019, a deflagration at a 2.16 MWh lithium-ion battery facility in Surprise, Arizona, seriously injured four career firefighters on a hazardous materials team. Before the explosion, the team measured dangerously high levels of hydrogen cyanide and carbon monoxide near the unit. The deflagration came about three minutes after the door was opened. The investigation recommended hazmat training focused on energy storage, remotely accessible gas monitoring and explosion prevention protection (UL FSRI report).

Before energization, the battery and hazmat plan should settle:

On that last point, federal law already gives the fire department a starting list. Under EPCRA Sections 311 and 312, a facility that must keep safety data sheets for hazardous chemicals, and holds them above threshold quantities, files an annual inventory with the state emergency response commission, the local emergency planning committee and the local fire department by March 1. The threshold is 10,000 pounds for most hazardous chemicals and the lower of 500 pounds or the threshold planning quantity for extremely hazardous substances (EPA, EPCRA Sections 311-312). A campus that energizes in the spring may not file its first inventory until the following March. Ask for the information before energization rather than waiting for the form.

Is there enough water, and can firefighters reach it?

Water supply is the question most often answered with an assumption. A new campus may be served by a water main sized for the buildings' sprinkler systems, by on-site tanks, or by both. The fire department needs to know which, along with the flow it can count on while sprinklers are also drawing.

Settle these points in writing:

If the answers point to a shortfall, the time to fix it is before energization, when the operator's construction budget and contractors are still on site.

How will responders get in?

Data center security is designed to keep people out, and it does that well. The fire department needs a way through it that works at 3 a.m. when the one security guard is handling the alarm.

The access plan should cover gate operation and override, a key box or equivalent at every entry point responders will use, a site map with building numbers that match what dispatch will say, and a staging location away from battery rooms and transformers. Walk it with the first-due company and the ambulance crew, not just the fire marshal. Check in-building radio coverage with the department's own portable radios, because large concrete structures can block signals.

The operator's own plan matters here too. OSHA requires employers with more than 10 employees to keep a written emergency action plan that includes procedures to account for all employees after evacuation and procedures for employees who stay behind to operate critical operations before they evacuate (29 CFR 1910.38). The fire officer arriving on scene needs that headcount and needs to know who, if anyone, is still inside working.

Who comes when the local department runs out?

A serious battery or electrical fire will outlast the first-due department's staffing. Most departments rely on mutual aid for anything that large, and the agreements are often old, informal or written for structure fires.

FEMA's resource management guidance treats mutual aid as the tool for filling identified capability gaps and suggests jurisdictions consider agreements with state, local, tribal and territorial organizations, nongovernmental organizations and private partners. It also stresses keeping resource inventories current and accurate (FEMA, NIMS Guideline for Resource Management Preparedness, June 2021).

Before energization, confirm that:

A pre-energization checklist

The work comes together in one sign-off meeting before energization. At that meeting, the operator, fire, EMS, law enforcement, emergency management and dispatch should confirm:

  1. The pre-incident plan is complete and loaded where crews can reach it on scene.
  2. The battery emergency response plan is reviewed and the gas monitoring display is located.
  3. The hazardous materials inventory is in the fire department's hands.
  4. Water supply is documented and tested.
  5. Access, keys, gates and radio coverage are tested by the responding agencies.
  6. Mutual aid and hazmat partners have toured the site.
  7. A tabletop exercise has walked through a battery fire and a medical emergency.

None of this requires a new program. It requires a date on the calendar, the right people in the room and the discipline to hold energization until the list is done.

Joel Yonkman is Principal Consultant of Emergency Response & Global Security Solutions (ERGSS), a national emergency management and security consulting firm. He served as Planning Section Chief on FEMA Region VI's Type 2 Incident Management Assistance Team from 2019 to 2023, was a primary instructor at the DHS Center for Domestic Preparedness, and began his career in the fire service and tactical EMS. He holds an M.S. in Disaster Medicine and Management from Philadelphia University.