The first written Incident Action Plan on a growing incident is usually the hardest one. The initial response is still running on radio traffic and memory. Resources are arriving faster than anyone can track them. And someone in the command post has been told to "get an IAP out" before the next shift.

The good news is that the process is the same on a county flood, a hazardous materials release or a federal disaster response. I worked it as a Planning Section Chief on FEMA Region VI's Incident Management Assistance Team, and I have taught it to federal teams as an ICS instructor. The steps below are the ones that produce a plan people can actually use.

What an IAP is, and what it is not

The National Incident Management System defines an Incident Action Plan as an oral or written plan containing the objectives established by the Incident Commander or Unified Command and addressing tactics and support activities for the planned operational period, generally 12 to 24 hours (FEMA, NIMS Third Edition, October 2017, p. 65).

Two words in that definition matter. Oral or written: a small incident can run on a verbal plan. Operational period: the IAP covers a defined block of time, not the whole incident. A 40-page document that tries to cover the next week is not an IAP. It is a strategy paper that nobody on the line will read.

Start with the leg of the Planning P

Incident action planning is not a FEMA invention. It is part of the Incident Command System, and the National Incident Management System made ICS the common standard for every level of government after September 11, 2001. FEMA was tasked with training the nation's responders in it, and FEMA follows the same doctrine on its own incidents. The planning process is drawn as the letter P. The leg covers the initial response: the incident occurs, notifications go out, responders make the initial response and assessment, the Incident Commander gives an incident briefing using the ICS 201, and the IC or Unified Command holds an initial meeting (FEMA EMI, IS-453, NIMS Planning P). These steps happen once. During this phase, the IC typically develops a simple plan and communicates it through concise oral briefings (FEMA, Incident Action Planning Process, March 2018).

The ICS 201 Incident Briefing is the bridge into the first written plan. It holds a map or sketch, a situation summary with a health and safety briefing, current and planned objectives, current and planned actions, strategies and tactics, the current organization, and a resource summary. The ICS 201 can serve as part of the initial Incident Action Plan (FEMA, NIMS ICS Forms Booklet, FEMA 502-2, September 2010).

That last point is the one most often missed. If the first operational period has to start before a full planning cycle can run, a complete, current ICS 201 is a legitimate plan. Do it well rather than rushing an incomplete set of IAP forms.

Then run the loop

Once the incident moves into longer-term planning, the loop of the P starts. FEMA's version lists these steps in order:

  1. Objectives development or update. The IC or UC sets objectives for the first operational period, then reviews and updates them each period.
  2. Strategy meeting or Command and General Staff meeting. The IC or UC gives direction to the Command and General Staff.
  3. Preparing for the tactics meeting. The Operations Section Chief and staff develop tactics and work out the resources to apply.
  4. Tactics meeting. Operations leads, with Logistics, the Safety Officer and Planning, to review proposed tactics and plan resource assignments.
  5. Preparing for the planning meeting. Staff identify support needs and assign specific resources.
  6. Planning meeting. Final review of the plan; the Command and General Staff confirm they can support it.
  7. IAP preparation and approval. The IC or UC approves the plan once all elements concur.
  8. Operational period briefing. Supervisors receive the IAP and then brief their assigned personnel.

Execution and assessment then feed the next round of objectives (FEMA, Incident Action Planning Process).

How the forms connect: 201 to 215 and 215A to 204

The forms are not paperwork for its own sake. Each one feeds the next.

ICS 202, Incident Objectives. Objectives go here, ideally in priority order, and they should be specific, measurable, action-oriented, realistic and time-sensitive. The Operational Period Command Emphasis block is not a narrative on the objectives; it says where to place emphasis during the period (ICS Forms Booklet).

ICS 215, Operational Planning Worksheet. The 215 communicates the decisions the Operations Section Chief makes in the tactics meeting about resource assignments and needs for the next operational period. The Resources Unit uses it to complete the ICS 204 Assignment Lists, and the Logistics Section Chief uses it to order resources.

ICS 215A, Incident Action Plan Safety Analysis. The Safety Officer prepares the 215A, usually working with the Operations Section Chief, to complete an operational risk assessment, prioritize hazards and develop controls. It is closely linked to the 215 and used alongside it in the tactics meeting (ICS Forms Booklet).

ICS 204, Assignment List. The 204 tells each Division and Group Supervisor what their assignment is once the Command and General Staff agree to it (FEMA, ICS Form Descriptions). This is the page a division supervisor reads. If the 204 is wrong, the plan is wrong where it counts.

The forms typically included in an IAP are the ICS 202, 203 (Organization Assignment List), 204, 205 (Incident Radio Communications Plan) and 206 (Medical Plan), with the 205A and 208 Safety Message as optional additions (ICS Forms Booklet). The 215 and 215A are not on that list. They are working documents that produce the plan.

Common mistakes in the first operational period

FEMA's Incident Action Planning Guide (January 2012) flags several of these directly. It warns that leaders must not let the forms become the primary focus of planning, that if everything is a priority, nothing is a priority, and that objectives should be clear, measurable and achievable without micromanaging. It also advises removing objectives once achieved rather than renumbering them each period (FEMA, Incident Action Planning Guide, January 2012). The point is the process, not the paperwork. The forms are where the process gets captured; they are not the process itself.

The mistakes I see most often in exercises and real events follow from those warnings:

Set an operational period the incident can support

The length of the operational period is a planning decision, not a default, and it has to be realistic and measurable. Objectives drive strategy and tactics, so the period should match how often the objectives need to change. Early in an incident, conditions shift fast and objectives need frequent adjustment, so periods are short. As the incident stabilizes, objectives change less and the operational period naturally extends. The more technical the operation, such as a hazardous materials entry or a technical rescue, the shorter the period you should expect. Whatever its length, the first IAP has to be complete, accurate and on time. Get the objectives right, run a real tactics meeting even if it lasts 20 minutes, build the 204s from the 215, and brief it. The second operational period will be easier because the first one was honest.

Joel Yonkman is Principal Consultant of Emergency Response & Global Security Solutions (ERGSS), a national emergency management and security consulting firm. He served as Planning Section Chief on FEMA Region VI's Type 2 Incident Management Assistance Team from 2019 to 2023, was a primary instructor at the DHS Center for Domestic Preparedness, and began his career in the fire service and tactical EMS. He holds an M.S. in Disaster Medicine and Management from Philadelphia University.